SR 179 - Project #2, Forest boundary to Sedona – Old vehicle bridge demolition complete; 2-way traffic on new bridge, last 2 major retaining walls 75% complete, substantial completion expected mid April.
-
Airport Road @ 89A Intersection Improvements (turn lanes, traffic signal) - Last required clearance received and design package to C & S but they are concentrating on large ARRA projects. Still no estimate for bid advertisement date.
-
SR 89A West Sedona Street Lighting - In design for July advertisement with W. Sedona Pavement Preservation project.
-
SR89A W. Sedona Pavement Preservation (FY11) - In design and schedule for bid advertisement July 2010 with Sedona Lighting project. JPAs with City of Sedona in review. Consultant design of sidewalk ramp updates started.
-
I-17, McGuireville Rest Area - Evaporation ponds liners installed; septic system installation in progress. I-17 southbound paving will not start until spring. Is still listed under temporary closed.
-
ARRA Projects - Looking forward to administering the Cornville Rd. project for the County.
-
I-17 DCR - Wildlife crossing recommendations and preliminary traffic report have been distributed. Initial DCR and draft EA scheduled for release anytime.
-
SR 260 Safety Improvement Project - Doing some spot repairs.
-
McGuireville TI - Some lane closures happening. Project on schedule and going well.
-
89A, Cement Plant to Black Hills project - Working on some minor issues. Statewide Stormwater Discharge Permit – On going. Makes ADOT storm water management enforcers.
-
I-17 Climbing Lane from Camp Verde to top of Copper Canyon - Just being kicked off. Doing some helicopter geological surveys. Deciding what to do with the turn out at the top of the canyon, not up to standards.
-
Black Canyon City to Cordes DCR - Priority out of Phoenix. Ahead of the I-17 DCR going to Flagstaff. Should be 4 lanes down and 5 lanes up. Looking into design options.
-
Cordes Junction - $52 M project. Sending out for Request for Proposals. Holding on environmental clearance.